Asked | Open questions | Answered
Points Date Pair Term / Answer given Level Status Gloss
- Mar 26 '15 jpn>eng 歩掛 [...] input component cost pro closed no
4 Mar 23 '15 jpn>eng 未成バランス Cash balance available to complete construction(s) in progress pro closed no
4 Mar 20 '15 jpn>eng ステップバー方式 Slide rail method pro closed no
- Oct 7 '14 jpn>eng 完成検査ピット工事 excavation of a pit for completed work inspection pro closed ok
- Sep 3 '14 jpn>eng 落掘 Subsidence from cavitation pro closed ok
4 Jul 20 '14 jpn>eng 杭打ち基礎上コンクリート梁形式 'concrete beams over pile foundation' type pro closed no
- Jul 16 '14 jpn>eng ダクターチャンネル (lighting) tracks pro closed no
- Jul 1 '13 jpn>eng ○ 正 All OK/Fine/No problem; Correct/Passed pro closed no
4 May 14 '13 jpn>eng 液体クサビカ "liquid wedging power" pro closed no
- Apr 18 '13 jpn>eng メガソーラー接続量 Number of panel connections of mega solar power plant pro open no
- Aug 9 '12 jpn>eng 引込み線用遮断機 Main's circuit breaker pro closed ok
4 Jun 23 '12 jpn>eng フラッシュレイク flash rake, or flash legs pro closed no